File #: 2021-0205    Version: 1 Name:
Type: Action Item Status: Passed
File created: 4/13/2021 In control: Board of Port Commissioners
On agenda: 10/12/2021 Final action: 10/12/2021
Title: A) ORDINANCE AMENDING THE FISCAL YEAR 2022 BUDGET INCREASING THE EQUIPMENT OUTLAY AND OTHER CAPITAL PROJECTS APPROPRIATION BY $350,000 FOR AN INCREASE TO THE U.S. COAST GUARD PHASE II TENANT IMPROVEMENTS PROJECT TO BE FUNDED FROM THE U.S. COAST GUARD/GENERAL SERVICES ADMINISTRATION (GSA) REIMBURSEMENT OF $350,000. B) RESOLUTION APPROVING CHANGE ORDER NO. 4 FOR $400,000 FOR CONTRACT NO. 2019-38, U.S. COAST GUARD PHASE II TENANT IMPROVEMENTS PROJECT, AND INCREASING THE APPROVED PROJECT BUDGET BY $350,000, PURSUANT TO BPC POLICY NO. 110, FOR A NEW TOTAL PROJECT BUDGET OF $3,800,000. A MAJORITY OF THIS INCREASE IS ATTRIBUTABLE TO U.S. COAST GUARD REQUESTED MODIFICATIONS AND IS ANTICIPATED TO BE REIMBURSED BY THE GENERAL SERVICES ADMINISTRATION PURSUANT TO THE LEASE.
Attachments: 1. 5. 2021-0205 Attachment A, 2. 5. 2021-0205 Draft Ordinance, 3. 5. 2021-0205 Draft Resolution
DATE: October 12, 2021

SUBJECT:

Title
A) ORDINANCE AMENDING THE FISCAL YEAR 2022 BUDGET INCREASING THE EQUIPMENT OUTLAY AND OTHER CAPITAL PROJECTS APPROPRIATION BY $350,000 FOR AN INCREASE TO THE U.S. COAST GUARD PHASE II TENANT IMPROVEMENTS PROJECT TO BE FUNDED FROM THE U.S. COAST GUARD/GENERAL SERVICES ADMINISTRATION (GSA) REIMBURSEMENT OF $350,000.

B) RESOLUTION APPROVING CHANGE ORDER NO. 4 FOR $400,000 FOR CONTRACT NO. 2019-38, U.S. COAST GUARD PHASE II TENANT IMPROVEMENTS PROJECT, AND INCREASING THE APPROVED PROJECT BUDGET BY $350,000, PURSUANT TO BPC POLICY NO. 110, FOR A NEW TOTAL PROJECT BUDGET OF $3,800,000. A MAJORITY OF THIS INCREASE IS ATTRIBUTABLE TO U.S. COAST GUARD REQUESTED MODIFICATIONS AND IS ANTICIPATED TO BE REIMBURSED BY THE GENERAL SERVICES ADMINISTRATION PURSUANT TO THE LEASE.
Body

EXECUTIVE SUMMARY:

Pursuant to Board of Port Commissioners (BPC) Policy No. 110, Board authorization is required for contract change orders in excess of 10% of the original contract award for contracts awarded in excess of two million dollars, but not in excess of ten million dollars. To date, three contract change orders have been processed at the staff level up to the 10% limit. Staff is seeking Board approval of contract Change Order No. 4 in the amount of $400,000 for a total construction contract value increase to $3,577,999.37 to allow the project team to deliver additional U.S. Coast Guard (Tenant) requested project scope that is reimbursable by General Services Administration (GSA) upon project completion. Change Order No. 4 funding is comprised of $50,000 from remaining project budget and an additional $350,000 from Tenant reimbursement. Board authorization will increase the U.S. Coast Guard Tenant Improvement Phase II total project budget to $3,800,000 from $3,450,000. Additionally, a District FY 2022 Budget amendment is also required to appropriate the additional $350,000 which is intended to be reimbursed by the Tenant.

On January 19, 2021,...

Click here for full text