File #: 2018-0565    Version: 1 Name:
Type: Action Item Status: Passed
File created: 12/12/2018 In control: Board of Port Commissioners
On agenda: 2/12/2019 Final action: 2/12/2019
Title: RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND AWARDING CONTRACT NO. 2018-03 TO DICK MILLER, INC. IN THE AMOUNT OF $7,999,999.99 FOR THE DEMOLITION AND SITE IMPROVEMENTS OF TRANSIT SHED 2 AND RAIL IMPROVEMENTS AT TENTH AVENUE MARINE TERMINAL - TIGER GRANT PROJECT, AS AUTHORIZED AND FUNDED BY THE BOARD IN THE FY 2019-2023 CAPITAL IMPROVEMENT PROGRAM
Attachments: 1. 4. 2018-0565 Attachment A, 2. 4. 2018-0565 Draft Resolution
DATE: February 12, 2019

SUBJECT:

Title
RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND AWARDING CONTRACT NO. 2018-03 TO DICK MILLER, INC. IN THE AMOUNT OF $7,999,999.99 FOR THE DEMOLITION AND SITE IMPROVEMENTS OF TRANSIT SHED 2 AND RAIL IMPROVEMENTS AT TENTH AVENUE MARINE TERMINAL - TIGER GRANT PROJECT, AS AUTHORIZED AND FUNDED BY THE BOARD IN THE FY 2019-2023 CAPITAL IMPROVEMENT PROGRAM
Body

EXECUTIVE SUMMARY:

This action recommends that the San Diego Unified Port District (District) Board of Port Commissioners (Board) approve the plans and specifications and authorize the award of a Capital Improvement Program (CIP) construction contract to Dick Miller, Inc. in the amount of $7,999,999.99 for the Demolition and Site Improvements of Transit Shed 2 and Rail Improvements at Tenth Avenue Marine Terminal Project. Funding for the project will come from two sources: The District's CIP and the U.S. Department of Transportation Maritime Administration's Transportation Investment Generating Economic Recovery (TIGER) Grant Program.

The plans and specifications define the contract work including the demolition of an obsolete and underutilized transit shed and headhouse adjacent to three of the terminal's eight primary vessel berths, disposal and salvage of the transit shed building and components, the excavation, grading and compaction of the areas under the demolished buildings to support a finished pavement system, site utility improvements, stormwater improvements, and rail improvements consisting of a rail lubricator system and air compressor assemblies.

The engineer's base bid construction cost estimate was $7,400,000.00. On December 11, 2018, the District received seven (7) bids ranging from $6,903,839.99 to $16,128,479.69. The lowest responsive and responsible bid was submitted by Dick Miller, Inc. in the amount of $6,903,839.99. In addition, Dick Miller's total bid including additive items is within the Project budget and allows award of the entire Pr...

Click here for full text