Title: A) RESOLUTION AUTHORIZING AMENDMENT NO.1 TO THE AS-NEEDED AGREEMENTS WITH TUCKER SADLER ARCHITECTS, INC. AND SILLMAN WRIGHT ARCHITECTS FOR ARCHITECTURAL AND ADA CODE COMPLIANCE REVIEW SERVICES, INCREASING THE AGGREGATE TOTAL BY $250,000 FROM $500,000 TO $750,000 WITH NO INCREASE REQUIRED TO THE FY2019 BUDGET. B) RESOLUTION AUTHORIZING AMENDMENT NO.1 TO INCREASE THE COMBINED BASE AMOUNT OF THE AS-NEEDED AGREEMENTS BY $300,000 WITH KTU+A AND SCHMIDT DESIGN GROUP, INC. FOR LANDSCAPE ARCHITECTURE SERVICES, INCREASING THE AGGREGATE TOTAL AMOUNT BY $300,000 FROM $500,000 TO $800,000 WITH NO INCREASE REQUIRED TO THE FY2019 BUDGET.
Attachments: 1. 9. 2018-0482 Attachment A, 2. 9. 2018-0482 Attachment B, 3. 9. 2018-0482 Attachment C, 4. 9. 2018-0482 Attachment D, 5. 9. 2018-0482A Draft Resolution, 6. 9. 2018-0482B Draft Resolution
DATE: November 6, 2018

SUBJECT:

Title
A) RESOLUTION AUTHORIZING AMENDMENT NO.1 TO THE AS-NEEDED AGREEMENTS WITH TUCKER SADLER ARCHITECTS, INC. AND SILLMAN WRIGHT ARCHITECTS FOR ARCHITECTURAL AND ADA CODE COMPLIANCE REVIEW SERVICES, INCREASING THE AGGREGATE TOTAL BY $250,000 FROM $500,000 TO $750,000 WITH NO INCREASE REQUIRED TO THE FY2019 BUDGET.

B) RESOLUTION AUTHORIZING AMENDMENT NO.1 TO INCREASE THE COMBINED BASE AMOUNT OF THE AS-NEEDED AGREEMENTS BY $300,000 WITH KTU+A AND SCHMIDT DESIGN GROUP, INC. FOR LANDSCAPE ARCHITECTURE SERVICES, INCREASING THE AGGREGATE TOTAL AMOUNT BY $300,000 FROM $500,000 TO $800,000 WITH NO INCREASE REQUIRED TO THE FY2019 BUDGET.
Body

EXECUTIVE SUMMARY:

On July 21, 2014, staff issued a Request for Qualifications (RFQ) for as-needed architectural and ADA code compliance services. Through the interview selection process, staff recommended authorizing agreements with the two highest-ranked firms, Tucker Sadler Architects, Inc. and Sillman Wright Architects.

On September 9, 2014, the Board authorized agreements with Tucker Sadler Architects, Inc. and Sillman Wright Architects for as-needed services for architectural and ADA code compliance review to support implementation of the District's program budgets.

The proposed action will increase the aggregate agreement capacity by $250,000. Since costs incurred under these agreements are funded under approved project budgets, there is no fiscal impact associated with the proposed action.

On May 17, 2016, a RFQ was issued for as-needed Landscape Architecture services and staff recommended authorizing agreements with the two highest-ranked firms, KTU+A and Schmidt Design Group, Inc.

On December 13, 2016, the Board authorized two-year agreements with KTU+A and Schmidt Design Group, Inc., for as-needed Landscape Architecture Services, up to a combined base amount of $200,000, necessary for implementation of the District's program budgets. These 2-year agreements also have the potent...